Chinese contractor seeks extra time to complete World Bank-funded roads in Uganda

 Chinese contractor seeks extra time to complete World Bank-funded roads in Uganda


Chinese contractor seeks extra time to complete World Bank-funded roads in Uganda


Chinese contractor is in search of extra time to complete World Bank-funded roads in Uganda. The seven roads consist of Lakidi Road, Philip Adonga Road, Janani Loum Road, Kitgum Road, Tom Apila and Oneka Roads all positioned in the Central division, Aya Hellen Dean positioned in Pandwong division, pronounced New Vision.

The Chinese firm, China Railway 18 Bureau Group Co Ltd, used to be given the contract for the work which used to be predicted to ultimate 18 months. The roads have been built beneath the World Bank-funded Uganda Support to Municipal Infrastructure Development Program (USMID).

The Chinese company was once accepted as a contractor for the multi-billion avenue works in March this 12 months after rising as the best-evaluated bidder, mentioned New Vision. Thomas Oketayot, the president of Kitgum Municipal Development Forum (MDF) stated that the contractor used to be granted a four-month contract extension duration via the neighborhood authorities ministry in September this 12 months with warning to end the works by way of January 30, said New Vision.


Oketayot says that the contractor won’t be capable to beat the November 30 deadline, which is much less than a month away. He stated MDF and the engineering branch of Kitgum municipal had obtained a minute of a website online assembly in which the challenge supervisor highlighted a viable extension duration of any other 4 months to January subsequent yr to totally whole the work, mentioned New Vision.


“Initially, the contract duration was once ending in November this year, however from that minute I saw the mission supervisor pronouncing there is a verbal exchange coming thru that the contract duration will be extended,” says Oketayot. Alex Abonga, the engineer at Kitgum municipality, says the contract length have to be prolonged so that the contractor covers the contemporary high-quality works. He stated that ending avenue works at Kitgum municipality can’t be rushed at the second to beat the November deadline, said New Vision.

Kitgum municipality is amongst eight new municipalities that commenced benefiting from a USD 350 Million World Bank-funded mission in 2019. (ANI)